Better repairs start with better planning.
Most repair conversations focus on the job itself: triaging, scheduling engineers and, increasingly, dealing with IoT alerts. Those matter, but they all start too late. Very few repairs are genuine freak accidents; most are building pathologies playing out as expected, such as components pushed beyond their intended lifecycles, usually because of budget pressures and trade-offs.
Deferring a replacement is a planning decision, not a repair one. Too often, it’s made in one programme without regard for what another programme is about to do to the same home. A roof replacement is pushed back a year to stay within budget, yet the energy programme then fits solar panels to that roof. Months later, a leak is reported and the panels must be removed before the roof can be done properly. Three teams, three budgets, one home and a repair nobody needed.
If we want fewer repairs, we must start fixing things before we log the repair.
Multiple plans & one home
Within most housing providers, different teams own capital works, planned maintenance and energy/retrofit programmes, and they each live in a different system and are funded from different budgets. Each plan is built on sound logic: stock-condition data and component lifecycles drive the capital programme; cyclical servicing and compliance drive planned maintenance; and EPC targets, funding windows and net-zero commitments drive the energy programme.
The trouble is that all three land on the same homes and often on the same components, typically the roof, walls, windows and heating.
I first saw this in a customer-facing consultancy role. When we put the housing provider’s capital works, planned maintenance and net-zero plans side-by-side, the same homes kept appearing in all three, often with works years apart that should have happened together. Each plan made sense on its own but together, they made no sense at all.
Nobody intentionally plans in isolation. Funding streams arrive with their own rules and deadlines, regulatory drivers pull in different directions and different teams are measured on delivering their own particular programmes. Above all, the data sits in different places so no single person gets to see the full picture of a single home.
Disconnected planning & longer backlogs
When plans don’t talk to each other, you can see the consequences in the queue of repairs, and they tend to fall within one of five common patterns.
- Duplicated visits – each programme is mobilised separately, so access, scaffolding, enabling works and resident liaison get paid for more than once on the same home.
- Bad timing – a component is replaced just before a retrofit disturbs it or is deferred until just after one, such as a gas boiler goes in like-for-like, then a heat pump is planned for the same home three years later, or a new kitchen is fitted, then opened up again for internal wall insulation.
- Unintended consequences – fabric upgrades without matching ventilation trap moisture, leading to condensation, damp and mould, so planned work ends up generating reactive work.
- Patching instead of planning – “It might be in next year’s programme” is one of the most expensive phrases in asset management; elements get patched repeatedly while they wait for a programme slot that keeps moving.
- The residents’ experience – for tenants, they only see one landlord. Repeated disruptions erode trust and drive complaints, regardless of which team caused it.
Joined-up planning
Joining up different planning threads doesn’t need a new department. It needs one view of each home, with condition, component lifecycles and energy measures in the same place, and a practice of checking the plans against each other before sign-off.
In practice, that means sequencing work so that dependent jobs happen in the right order: roof before solar, fabric before heating, and ventilation alongside insulation. It means bundling interventions into one visit when access, scaffolding, or disruption can be shared. And it means making deferral decisions knowingly, with the knock-on costs visible to everyone.
It can also reveal work you don’t need to plan. Sometimes a home’s existing planned programme, such as a window replacement already due, is enough to meet its energy target on its own. Spotting that early stops retrofit money being spent twice on the same outcome.
The payoff
The benefits compound because fewer repeat visits mean fewer reactive jobs and shorter backlogs. Maintenance spending becomes more predictable and retrofit funding goes further because it doesn’t undo or duplicate other work.
Housing providers are better positioned regarding compliance and energy targets because they can show how each home gets there, and residents see fewer contractors, less disruption and a landlord that looks like it has a cohesive plan.
Start before the repair
This is the problem we kept running into in consultancy and why we developed our solution in a product called Navigator. By bringing each home’s capital, maintenance and energy plans into one place, you can take a whole-property approach.
You don’t need new software to start, though. Before signing off next year’s programmes, put the capital, planned maintenance and energy plans for the same homes side-by-side (even in a spreadsheet) and look for clashes. Each one you find is a future repair that you can plan out of existence.
Faster repairs matter, but the quickest repair is the one that never needs to happen.
Samuel Lott is the product owner for Navigator at Infoshare+.